26 April 2018

Temple Point
Bristol

  • Region: Bristol
  • Client: Legal & General Group Plc
  • Value: £6,484,885
  • Contract term: JCT Design & Build 2011 with (Legal & General) bespoke amendments
  • Contract length: 50 weeks
  • Procurement: Design + Build
  • Completed: April 2018

Project Information

This design and build project comprised a phased refurbishment and Cat B fit out works, to an occupied office building in Bristol city centre. Located in a prominent position in proximity to Temple Meads train station, Network Rail sublet the building and remained in occupation throughout the project.

Midas completed the works to this five-storey building in phases to mitigate disruption to the building’s tenants, with sectional handover to the customer.

Works included a demolition soft strip; increasing the height of reception from 1.5 to two storeys; full refurbishment; removal of the terracotta fin over the reception; extending the new two-storey glazed façade to wrap the entrance plaza and new reception; increasing the bike storage provision and cycling routes; and upgrading the landscaping.

The project achieved BREEAM Very Good.

 